Project Overview:
Croda Rawcliffe bridge engaged OLG May 2025 to support two projects. One was to relocate some existing pumps for a tanker loading facility and the other project involved the design and installation of a new lifting beam.
OLG have provided a full design pack for these two solutions, now working on the installation tied-in into existing plant. The civils are being delivered by another on site contractor (drainage), but OLG are looking to deliver the mechanical fabrication and installation in the coming months.
Scope of Works:
- Detailed Design – Process, Civil/Structural, Mechanical/Piping, Stress as fit for construction design pack
- Fabrication, Mechanical installation
- Value: £100k
- Duration: 3 months