Skip to content Skip to footer
Back to homepage

Case Study - Cemex

Cemex

Project

Plant and Electrical Distribution

Project: Plant and Electrical Distribution

A tidal surge flooded a large cement manufacturing site causing extensive damage to the electrical infrastructure. Switchgear, transformers and cabling deemed damaged beyond repair.

  • Surveys, provisional fault studies and initial designs
  • Development of equipment specification, cable infrastructure and new earthing systems
  • Design of the protection scheme
  • Assistance during installation and commissioning

Other Projects

  • Short circuit fault and discrimination study
    (11kV feed)
  • Short Term Operating Resource site, sizing of
    11 kV and 415 V supply and earth cables
  • Review of 6.6 kV MCC Protection Scheme
  • Distribution board specification & outgoing cable sizing for oil refinery improvements