Case Study - Babcock Wanson

Babcock Wanson

Sector

Construction

Project Overview


OLG were engaged by Babcock Wanson to provide containerised thermal fluid system and boiler for Knauf, Immingham.

This plantroom will serve as a permanent replacement for the temporary boiler system that was previously in place. After six months of meticulous planning, coordination, and collaboration, OLG successfully integrated the containerised system into existing plant with no impact on existing production or loss time injuries.

Most of the mechanical works were delivered in OLG’s workshop (in a controlled environment), reducing the need for a large construction area and on-site activities.

Scope of Works

  • Fabricate all the pipework associated with thermal fluid system and containerised boiler
  • Install all the equipment within a container – providing a drop in solution for Knauf
  • Mechanically install all the equipment and tie-in to existing plant
  • Value: £250k
  • Duration: 6 months
  • Utilisation: 8 mechanical technicians